|
PARK UPDATE - MARCH/APRIL 2008
BID AWARDED FOR PARKS
The Chester Square Area
Neighborhood Association received word this week that the
bid for complete renovation of the twin parks in the square
has been awarded. The successful bid, one of ten received
by the Boston Parks Department, will allow the landscaping
plan for the parks to be implemented in permanent granite.
The design is described as a simple plan
that echoes the Victorian history of the area with two three-tier
Victorian cast-iron fountains, central plazas with circular
seating, meandering paths through the linear parks and a
slight raising of the level of the ground on the sides of
the parks facing the heavy traffic on Massachusetts Avenue.
This rise in level will provide some buffer from cars and
trucks for those sitting on benches or seating walls in
the parks. A number of flowering trees are included in the
design and large planters will provide additional shelter
from the sight of traffic at the plazas.
Residents of the area, who have been
working on the reconstruction of the parks for six years,
were delighted with the news. Neighbors of the parks had
lobbied city councilors, applied for grants, inspected dozens
of other parks in the city for ideas, and worked closely
with the Parks Department on the project. In the course
of their effort to beautify the two parks, residents and
the Association had received a grant from the Browne Fund
for landscape design, a community benefit package from the
BRA to install Victorian lights in the parks, a second Browne
Fund grant to restore fountains to the parks and a capital
budget allocation from the Parks Department. The awarding
of the bid is the last step in making the renovation of
the parks a reality.
It is expected that ground will be broken
for the construction of the parks in early spring and it
is hoped that the project will be completed by fall.
-------------------------------------------------------
PARK UPDATE AUGUST 2007
Members of the Parks Committee
of CSANA held a short strategy meeting on August 1 to prepare
for the August 2 meeting with Parks and Recreation on fiscal
shortfalls in the parks' renovation project. The estimates
completed by the engineering company hired by the city indicate
that the whole project would cost $750,000, while the City
Council only allocated $500,000.
After lengthy discussions, it was decided
that all underground construction work, such as water and
electric lines, foundations for fountains and walls etc.
should receive priority while plantings could be delayed
if funds run out. The theory is that it would make no sense
to disrupt newly planted landscaping to install something
like pipes for the fountains or any other below ground utility
at a later date.
In addition, there is the question of
timing. If the parks' renovation is tied to the reconstruction
of Mass. Ave. it is possible that there would be some economies
of scale. The question is whether the Mass. Ave. project
retains its slot on the T.I.P. list and if so whether construction
would begin in '08 or '09. The final vote on the construction
list will take place on August 16.
Expensive or custom made benches were
rejected in an effort to hold down costs. There is also
some question about using some of these funds to repair
the fences around the parks since they were just sandblasted
and painted by the city.
CSANA MEETING WITH PARKS AND RECREATION
8/2/07
The meeting was held at 1010 Mass. Ave.,
the office of Boston Parks and Recreation. Attending were:
Angela Murray, project manager of the parks' renovation
for Parks and Rec, John Ryther of Icon Engineering, who
prepared the engineering design and estimates, CSANA President
Ben Garvin, and Sheila Cheimets and Jill Young of the Parks
Committee.
The cost breakdowns discussed included
the following:
1) Costs that cannot be avoided such as
permits and bonds, demolition and site preparation and earthwork.
2) Costs that could be deferred, such
as brick paths. The less costly alternative would be to
lay out concrete paths which would be set slightly below
ground level and be used as the foundation for brick paving
at a later date. Other costs that could be put off include
ornamental gates for the parks and granite posts on each
side of each entrance.
3) Costs that could be rejected altogether
such as expensive, decorative trash receptacles, bike racks,
and pyramid caps on the present fencing.
Among the major issues is whether to
build the retaining walls and bases and basins for the fountains
out of granite (the most costly alternative) cement with
a granite veneer (less costly) or cement alone. Because
some elements of the design are curved in shape, cement
alone is not much less in cost and of course would have
a much shorter life span.
In the discussion, Ms Murray noted that
there were some amenities (like bike racks) that she might
be able to place in the parks at no cost and that there
might well be grants made by such entities as the Browne
Fund that would help defray some of the proposed costs.
In addition, she will put the project out to bid in Winter
when bids generally come in lower and would discuss with
the DPW the possibility of extending stubs from their work
on Mass. Ave. to the parks.
It was decided that CSANA will apply
to the Browne Fund for additional grant funding for the
parks; Parks and Rec will continue their discussions with
the DPW and Icon Engineering will provide information on
other grant programs that offer funding for similar projects.
A revised cost estimate that omits rejected items will also
be prepared.
The group will meet again when there is further information
about funding efforts.
-------------------------------------------------------
CITY COUNCIL APPROVES FUNDING FOR CHESTER
SQUARE - JULY 2007
After a favorable budget hearing before
the City Council Budget Committee, the full Council voted
unanimously to approve $500,000 in funding for Chester Square
parks. The money was contained in the Parks and Recreation
capital budget.
The Chester Square Area Neighborhood Association
representative had testified at the hearing on the budget
on Friday, June 15th; the vote was taken some weeks later
as part of the overall city budget.
The amount contained in the budget for
the renovation of the parks in Chester Square is considerably
less than the $600,000 in costs that had been estimated
for completion of the whole project. Parks Commissioner
Toni Pollack was questioned on the funding disparity by
City Councilor Michael Flaherty.
The Commissioner said that she was fully
supportive of the project and that there would be funds
to complete it coming from two sources. One, she said, was
reversionary monies left over from other park projects in
the South End; the other was a negotiation currently underway
to have the city's Department of Public works install the
wiring for the fountains and the water lines both for fountains
and for hose bibs. These pieces, she said, would allow the
two parks to be renovated completely.
Stan Ivan, Director of Construction for
Parks and Rec. confirmed for the Council members that he
was in negotiations with the DPW when called on by the Commissioner.
The CSANA Parks Committee is now
awaiting a meeting with the engineering company hired by
the city to turn the conceptual park plan into engineering
documents that can be used to go out for bids on the work.
That meeting will review the details of the plan such as
design of the fountains and benches and location of such
amenities as flowering trees and flower beds.
-------------------------------------------------------
CITY COUNCIL
BUDGET HEARING ON
CHESTER SQUARE PARKS' FUNDS
Friday, June 15, 2007
Sheila Cheimets attended the hearing.
Apparently the Parks and Recreation Department
intends to put together the funding for renovating the two
parks in Chester Square from a number of sources, only one
of which is their capital budget.
This is the information that emerged from
the budget hearing held last Friday by the Budget Committee
of the City Council, at which both Commissioner Toni Pollak
and Director of Engineering and Construction Stan Ivan testified.
Although members of the CSANA Parks Committee
had thought that all of the $600,000 estimated for the parks'
renovation would be included in the Park and Rec capital
budget for the upcoming fiscal year, Councilor Michael Flaherty
discovered during the hearing that only $500,000 had been
included for Chester Square. He raised the issue during
testimony by the Commissioner and was told that the remaining
costs would be covered by getting the Boston Department
of Public Works to pay for the installation of wiring for
the fountains and a piped-in water supply for the fountains
and hose bibs.
In addition, Director Ivan said that there
were funds left over from other South End park projects
that "have been committed" by the Commissioner
to the CSANA project. What Parks and Rec is still awaiting
is agreement from DPW that they will in fact undertake to
pay the two costs.
Councilor Flaherty asked that the agreement
between the DPW and Parks and Rec on Chester Square costs
be made final before the council votes on the overall budget
which it will do in two weeks, so that he can be assured
that there is sufficient funding for the project in the
next fiscal year.
The good news is that there were no adverse
questions raised about the parks project; the only questions
had to do with making sure there is sufficient funding to
accomplish it in one year's budget.
The bad news is as follows:
- we don't know if DPW will agree to install the wiring
for the fountains and the water pipes
- will we have an answer about this before the vote in two
weeks?
- if they do agree, does that mean construction on our parks
won't begin until the renovation of Mass. Ave. is begun?
(Scheduled on the TIP list for 2008, last we heard)
I checked with director Ivan after
the hearing and he tells me that although the park is fully
wired for lights, they can't take power for the fountains
off this wiring. He didn't say why. The fountains must be
circulating so both water and electricity are needed for
each fountain. I will check with Councilor Flaherty's office
as well as with the Commissioner to find out whether or
not they have received agreement from the DPW.
|